Pre-Handover (PCI) Inspections in Deanside

Handover in Deanside usually arrives with a date, a walk through with the supervisor and a form to sign. We go through the same house first, slowly, and hand you a numbered list to send back before you accept it.

  • Numbered list for your builder
  • Every door opened and closed
  • Roof and gutters checked from above
  • Insulation checked where reachable
  • Contract and tolerances referenced
  • Report the day after the visit
  • Re-inspection before you sign
  • Inspector on the phone afterwards
Request a quoteSend your details and an inspector will ring you back.

No obligation. We use your details for your quote and may contact you about it even if you don't finish.

Fully licensed & accredited

What is included

What is included in a Deanside pre-handover (PCI) inspection

A Deanside PCI is assessed against your contract, plans and colour selections, the NCC and ABCB Housing Provisions, the Guide to Standards and Tolerances 2015, AS 3740 for wet areas and AS 3700 for brickwork. Fixtures are operated by hand only.

Doors and hardware

  • Swing clear of the frame
  • Latch into the striker
  • Sit flush when closed
  • Top and bottom edges painted

Brick and cladding

  • Mortar joints filled
  • Gaps at junctions sealed
  • Articulation joints full height

Roof from the outside

  • Cracked or broken tiles
  • Underlaps and pointing
  • Cladding complete

Gutters and downpipes

  • Brackets clipped
  • Downpipes fixed to walls
  • Debris cleared from gutters

Roof space

  • Batts sitting tight together
  • Nothing pushed aside by trades
  • Access hatch fitted

Bathrooms and laundry

  • Grout and silicone finish
  • Toilet fixed firm to the floor
  • Screens and wastes

Joinery

  • Chips and scratches
  • Doors and drawers aligned
  • Benchtop joins

Paint and plaster

  • Patchy coats
  • Nail pops and joins
  • Sealant beads neat

Outside the house

  • Paths and driveway intact
  • Ground falling away from walls
  • Site cleaned

28 checkpoints across 9 areas on a standard Deanside pre-handover (PCI) inspection. Anything locked, stacked with materials or unsafe to reach on the day is named in the report as not inspected, never quietly passed.

Sample findings

Sample defects found during our pre-handover (PCI) inspections near Deanside

Ten items picked from a finished house over the road in Aintree: doors, external joints, roof and finishes, the kinds of things a quick walk through tends to miss.

Internal door binding against its frame instead of swinging freely, found during a pre-handover inspection in Aintree
Internal door binding against its frame instead of swinging freely, Aintree
Door sitting proud of its frame instead of closing flush, found during a pre-handover inspection in Aintree
Door sitting proud of its frame instead of closing flush, Aintree
Door top and bottom edges left unpainted, so the timber can swell and warp, found during a pre-handover inspection in Aintree
Door top and bottom edges left unpainted, so the timber can swell and warp, Aintree
Open joint in the external wall, left without sealant at handover, found during a pre-handover inspection in Aintree
Open joint in the external wall, left without sealant at handover, Aintree
Roof cladding still incomplete at the handover inspection, found during a pre-handover inspection in Aintree
Roof cladding still incomplete at the handover inspection, Aintree
Gaps in the ceiling insulation where batts have been pushed aside, found during a pre-handover inspection in Aintree
Gaps in the ceiling insulation where batts have been pushed aside, Aintree
Rough, smeared sealant that needs redoing to a neat, even finish, found during a pre-handover inspection in Aintree
Rough, smeared sealant that needs redoing to a neat, even finish, Aintree
Window rubber flashing needing adjustment so it seals against the cladding, found during a pre-handover inspection in Aintree
Window rubber flashing needing adjustment so it seals against the cladding, Aintree
Mortar joints with holes that let water into the brick cavity, found during a pre-handover inspection in Aintree
Mortar joints with holes that let water into the brick cavity, Aintree
Toilet cistern loose and rocking on the pan, found during a pre-handover inspection in Aintree
Toilet cistern loose and rocking on the pan, Aintree
Our inspectors reviewing a report together
Why Deanside owners choose us

Independent. Licensed. Insured.

  • The inspector who walks your Deanside house is the one who writes and signs the report.
  • Findings are measured against your contract, the NCC and the Guide to Standards and Tolerances 2015.
  • Wind exposure on open Melton ground makes bracing and tie-down a priority at every frame visit.
  • Questions after the report go straight to the inspector, by phone, for as long as the build runs.
Guides

Pre-Handover (PCI) Inspections guides for Deanside

All guides →

Book pre-handover (pci) inspections in Deanside

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Pre-Handover (PCI) Inspections in Deanside: common questions

How close to handover should a Deanside PCI be booked?

Roughly a week before the date your builder gives you. That leaves time for the builder to read the list and act on it before you are asked to sign.

Does the PCI cover the electrical, gas and plumbing systems?

No. We do not energise circuits, test gas or pressure test plumbing, and we do not certify occupancy. Switchboards, wiring and smoke alarms are for a licensed electrician. Fixtures are operated by hand only and anything inaccessible is listed in the report.

My builder says an item on the list is fine. Now what?

Each item names the standard or tolerance it is measured against, which usually settles it. If it does not, ring the inspector, or book a defect investigation; for VCAT you would need an expert witness report.